 Brief Description of the Integration Project

 
  1. The System is launched by a joint Project Team that consists of specialists of the Bank and CFT, who can work both on-site and remotely.
  2. The Project consists of a set of sub-projects – "one Project for one Product".
  3. Each sub-project is aimed at a certain business result for the Bank and has a fixed LAUNCH DATE and PRODUCT PARAMETERS.
  4. Project Management:
    1. 4.1 Project Director​​ is the head of the Project on the part of CFT who is responsible for TIMELY launch of all Products necessary for the Bank.
    2. 4.2 Sub-project Co-director is the head of a sub-project on the launch of a certain Financial Product on the part of the Bank who is responsible for determination of the PARAMETERS and the DATE of installation of the respective Financial Product. As a rule, it is a head of the Bank business department with business plans concerning the scopes of attraction, placement, number of customers, margin etc.
    3. 4.3 Sub-project Coordinator is the head of a sub-project on the launch of a certain Financial Product on the part of CFT who is responsible for timely launch of the respective Financial Product and who coordinates the work of the specialists of CFT Project Team on the installation of the Financial Product.
  5. The launch of a Financial Product includes:
    1. 5.1 a sequence of stages (survey, acceptance tests, transfer and control support, end of month),
    2. 5.2 works on the setup, conversion, integration and customization of the Product in accordance with the specific requirements of the Bank.
  6. Weekly control of the Project progress.
    1. During the implementation of each sub-project, on a weekly basis, the Project Director on the part of CFT and Sub-project Co-director on the part of the Bank sum up the results of the previous week and coordinate and record the work plan (in accordance with the Product launch priorities) for the coming week.


System Launch Services​
 ​
  • Training
  • Installation of OS, DBMS, Platform
  • Estimation of the quality of initial data
  • Launch of Products/Applications
  • Integration of Applications
  • Modification of Products/Applications
  • Test days
  • Load testing
  • Control support
  • Consultation of generation of statutory reporting
  • Consultation on the end of month